A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:10
Which one of the following is most apt to align management's priorities with shareholders' interests? compensating managers with shares of stock that must be held for a minimum of three years holding corporate and shareholder meetings at high-end resort-type locations preferred by managers increasing the number of paid holidays that long-term employees are entitled to receive allowing employees to retire early with full retirement benefits paying a special management bonus on every fifth year of employment
Answers: 1
question
Business, 22.06.2019 09:40
Henry crouch's law office has traditionally ordered ink refills 55 units at a time. the firm estimates that carrying cost is 35% of the $11 unit cost and that annual demand is about 240 units per year. the assumptions of the basic eoq model are thought to apply. for what value of ordering cost would its action be optimal? a) for what value of ordering cost would its action be optimal?
Answers: 2
question
Business, 22.06.2019 13:10
Thomas kratzer is the purchasing manager for the headquarters of a large insurance company chain with a central inventory operation. thomas's fastest-moving inventory item has a demand of 6,000 units per year. the cost of each unit is $100, and the inventory carrying cost is $10 per unit per year. the average ordering cost is $30 per order. it takes about 5 days for an order to arrive, and the demand for 1 week is 120 units. (this is a corporate operation, and the are 250 working days per year.)a) what is the eoq? b) what is the average inventory if the eoq is used? c) what is the optimal number of orders per year? d) what is the optimal number of days in between any two orders? e) what is the annual cost of ordering and holding inventory? f) what is the total annual inventory cost, including cost of the 6,000 units?
Answers: 3
question
Business, 22.06.2019 14:00
How many months does the federal budget usually take to prepare
Answers: 1
You know the right answer?
A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start o...
Questions
question
Mathematics, 25.11.2021 06:00
question
Mathematics, 25.11.2021 06:00
question
English, 25.11.2021 06:00
question
Biology, 25.11.2021 06:00
question
Mathematics, 25.11.2021 06:00
Questions on the website: 13722361