Business, 24.06.2020 22:01 blacee01

Here is a list of activity times for a project as well as crashing costs for its activities. Determine which activities should be crashed and the total cost of crashing if the goal is to shorten the project by three weeks as cheaply as possible. There are three paths (top, middle and bottom). Each path contains three sequential activities which must be performed in the order they are listed (e. g., A before B, B before C). Note that Activity C is contained on both the top and middle paths. Path Activity Duration (weeks) First Crash Second Crash
Top A 5 $8 $10
B 6 7 9
C 3 14 15
Middle D 3 9 11
E 7 8 9
C 3 14 15
Bottom F 5 10 15
G 5 11 13
H 5 12 14

ansver
Answers: 1

Another question on Business

question
Business, 20.06.2019 18:04
Heating & cooling installs and services commercial heating and cooling systems. elklandelkland uses job costing to calculate the cost of its jobs. overhead is allocated to each job based on the number of direct labor hours spent on that job. at the beginning of the current year, elklandelkland estimated that its overhead for the coming year would be $ 61 comma 500$61,500. it also anticipated using 4 comma 1004,100 direct labor hours for the year.
Answers: 1
question
Business, 22.06.2019 03:00
Match the given situations to the type of risks that a business may face while taking credit.(there's not just one answer)1. beta ltd. had taken a loan from a bankfor a period of 15 years, but its salesare gradually showing a decline.2. alpha ltd. has taken a loan for increasing its production and sales,but it has not conducted any researchbefore making this decision.3. delphi ltd. has an overseas client. the economy of the client’s country is going through severe recession.4. delphi ltd. has taken a short-term loanfrom the bank, but its supply chain logistics are not in place.a. foreign exchange riskb. operational riskc. term of loan riskd. revenue projections risk
Answers: 1
question
Business, 23.06.2019 02:00
Suppose that a major city’s main thoroughfare, which is also an interstate highway, will be completely closed to traffic for two years, from january 2014 to december 2015, for reconstruction at a cost of $535 million. if the construction company were to keep the highway open for traffic during construction, the highway reconstruction project would take much longer and be more expensive. suppose that construction would take four years if the highway were kept open, at a total cost of $800 million. the state department of transportation had to make its decision in 2014, one year before the start of construction (so that the first payment was one year away). so the department of transportation had the following choices: (i) close the highway during construction, at an annual cost of $267.5 million per year for two years. (ii) keep the highway open during construction, at an annual cost of $200 million per year for four years. now suppose the interest rate is 80%. calculate the present value of the costs incurred under each plan.
Answers: 3
question
Business, 23.06.2019 02:00
Here are the expected cash flows for three projects: cash flows (dollars) project year: 0 1 2 3 4 a − 6,100 + 1,275 + 1,275 + 3,550 0 b − 2,100 0 + 2,100 + 2,550 + 3,550 c − 6,100 + 1,275 + 1,275 + 3,550 + 5,550 a. what is the payback period on each of the projects? b. if you use a cutoff period of 2 years, which projects would you accept?
Answers: 2
You know the right answer?
Here is a list of activity times for a project as well as crashing costs for its activities. Determi...
Questions
question
History, 26.03.2021 19:20
question
Mathematics, 26.03.2021 19:20
question
Mathematics, 26.03.2021 19:20
Questions on the website: 13722359