Business, 14.07.2020 22:01 ewalchloe5067920

"A production line is currently organized so that all parts go through an initial tuning" process. Each part that exits the tuning process goes to either inspector A or inspector B. Currently 50 parts per hour goes into the tuning station, 40% of which will later be sent to inspector A and 60% will be sent to inspector B. Each inspected part exits the inspection process either with a "pass" or "fail" result. Both inspectors reject about 30% of all units inspected. On average there are 30 units at the tuning station, 20 units at inspector A’s station, and 25 units at inspector B’ station. Assume that we have a stable process throughout.

a. What is the process flow time?
b. What is the average flow time of parts that go through inspector B?
c. What is the average flow time of parts that will pass the inspection?
d. Assume that the company above competes in an industry where high volume is an order qualifier. Use little’s law to explain specifically what the firm should focus on if it wants to have better flow time performance.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 17:00
Vincent is interested in increasing his earning potential upon completing his internship at a major accounting firm. which option can immediately boost his career in the intended direction? b. complete a certification from a professional organization c. complete a new four-year undergraduate program in a related field d. complete a two-year associate degree in a related field e. complete an online course in accounting
Answers: 3
question
Business, 22.06.2019 19:40
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
question
Business, 22.06.2019 21:10
You own a nonunion company with 93 nonexempt employees. all of these employ- ees pack books into boxes for shipment to customers throughout the united states. because of wide differences in performance, you have decided to try performance appraisal, something never done before. until now, you have given every worker the same size increase. now you want to measure performance and reward the best performers with bigger increases. without any further information, which of the five types of appraisal formats do you think would be most appropriate? justify your answer. do you anticipate any complaints, or other comments, from employees after you implement your new system?
Answers: 1
question
Business, 23.06.2019 02:40
James sebenius, in his harvard business review article: six habits of merely effective negotiators, identifies six mistakes that negotiators make that keep them from solving the right problem. identify which mistake is being described. the negotiator has neglected to consider the course of action he will take if the proposed deal is not possible.
Answers: 3
You know the right answer?
"A production line is currently organized so that all parts go through an initial tuning" process. E...
Questions
question
Mathematics, 09.09.2020 19:01
question
Social Studies, 09.09.2020 20:01
question
Mathematics, 09.09.2020 20:01
question
English, 09.09.2020 20:01
question
Mathematics, 09.09.2020 20:01
Questions on the website: 13722367