The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE TIME
PREDECESSOR (WEEKS)
A 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7
a. What is the critical path?
A-B-E-G
A-C-D-E-G
A-C-D-F-G
C-D-F-G
b. How many weeks will it take to complete the project?
Number of weeks
c. How much slack does activity B have?
Slack of activity B weeks

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:30
How do primary and secondary industries differ
Answers: 1
question
Business, 22.06.2019 07:10
mark, a civil engineer, entered into a contract with david. as per the contract, mark agreed to design and build a house for david for a specified fee. mark provided david with an estimation of the total cost and the contract was mutually agreed upon. however, during construction, when mark increased the price due to a miscalculation on his part, david refused to pay the amount. this scenario is an example of a mistake.
Answers: 1
question
Business, 22.06.2019 18:00
1. what is the amount of interest earned after two years on a $100 deposit paying 4 percent simple interest annually? $8.00 $4.08 $8.16 $4.00 2. what is the amount of compound interest earned after three years on a $100 deposit paying 8 percent interest annually? $24.00 $8.00 $16.64 $25.97 3. a business just took out a loan for $100,000 at 10% interest. if the business pays the loan off in three months, how much did the business pay in interest? $2,500.00 $10.00 $250.00 $10,000.00 4. what is the annual percentage yield (apy) for a deposit paying 5 percent interest with monthly compounding? 5.00% 5.12% 79.59% 0.42%
Answers: 1
question
Business, 22.06.2019 23:00
Draw a flowchart for a process of interest to you, such as a quick oil-change service, a factory process you might have worked in, ordering a pizza, renting a car or truck, buying products on the internet, or applying for an automobile loan. identify the points where something (people, information) waits for service or is held in work-in-process inventory, the estimated time to accomplish each activity in the process, and the total flow time. evaluate how well the process worked and what might be done to improve it.
Answers: 2
You know the right answer?
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE TIME
Questions
question
Biology, 24.04.2020 18:54
question
Chemistry, 24.04.2020 18:54
Questions on the website: 13722367