A project manager budgeted $6,000 for the work performed and has spent $8,000 to date. If they budgeted $10,000 for the work scheduled, what is the Cost Variance (CV)?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:50
At a roundabout, you must yield to a. already in the roundaboutb. entering the roundaboutc. only if their turn signal is ond. only if they honk at you
Answers: 1
question
Business, 22.06.2019 10:30
What are the positive environmental trends seen today? many industries are taking measures to reduce the use( _gold,carbon dioxide,ozone_) of -depleting substances and are turning to(_scarce,renewable,non-recyclable_) energy sources though they may seem expensive. choose one of those 3 option to fill the
Answers: 3
question
Business, 22.06.2019 18:00
What is the cause of smoky exhaust?
Answers: 1
question
Business, 22.06.2019 19:00
What is an equation of the line in slope intercept formm = 4 and the y-intercept is (0,5)y = 4x-5y = -5x +4y = 4x + 5y = 5x +4
Answers: 1
You know the right answer?
A project manager budgeted $6,000 for the work performed and has spent $8,000 to date. If they budge...