subject
Business, 30.07.2020 20:01 alkaline27

A stock has a beta of 1.15, the expected return on the market is 10.3 percent, and the risk-free rate is 3.1 percent. What must the expected return on this stock be? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e. g., 32.16.)

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 22:30
What is the connection between digital transformation and customer experience
Answers: 2
question
Business, 21.06.2019 23:30
Consider the following scenarios. use what you have learned to decide if the goods and services being provided are individual, public, or merit goods. for each case, state what kind of good has been described and explain your answer using the definitions of individual, public, and merit goods. (6 points each) 1. from your window, you can see a city block that's on fire. you watch city firefighters rescue people and battle the flames to save the buildings. 2. while visiting relatives, you learn that your cousins attend a nearby elementary school that is supported financially by local property tax revenue. 3. you see a squadron of military jets flying overhead. 4. you find out that your aunt works for a defense manufacturing company that has several defense contracts with the government. she tells you that she works for a team that is producing a communications satellite. 5. your class visits a local jail run by a private, profit-making company that detains county criminals and is paid with tax revenue.
Answers: 1
question
Business, 22.06.2019 09:30
Stock market crashes happen when the value of most of the stocks in the stock market increase at the same time. question 10 options: true false
Answers: 1
question
Business, 22.06.2019 14:20
Anew 2-lane road is needed in a part of town that is growing. at some point the road will need 4 lanes to handle the anticipated traffic. if the city's optimistic estimate of growth is used, the expansion will be needed in 4 years and has a probability of happening of 40%. for the most likely and pessimistic estimates, the expansion will be needed in 8 and 15 years respectively. the probability of the pessimistic estimate happening is 20%. the expansion will cost $ 4.2 million and the interest rate is 8%. what is the expected pw the expansion will cost?
Answers: 1
You know the right answer?
A stock has a beta of 1.15, the expected return on the market is 10.3 percent, and the risk-free rat...
Questions
question
Mathematics, 24.11.2021 14:00
question
Mathematics, 24.11.2021 14:00
question
Computers and Technology, 24.11.2021 14:00
question
History, 24.11.2021 14:00
Questions on the website: 13722362