Business, 31.07.2020 16:01 mimithurmond03

Thomas Textiles Corporation began November with a budget for 60,000 hours of production in the Weaving Department. The department has a full capacity of 75,000 hours under normal business conditions. The budgeted overhead at the planned volumes at the beginning of November was as follows: Variable overhead $450,000
Fixed overhead 262,500
Total $712,500
The actual factory overhead was $725,000 for November. The actual fixed factory overhead was as budgeted. During November, the Weaving Department had standard hours at actual production volume of 64,500 hours.
Determine the variable factory overhead controllable variance and the fixed factory overhead volume variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Round your interim computations to the nearest cent, if required.
a. Variable factory overhead controllable variance: $
b. Fixed factory overhead volume variance: $

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 03:30
Acrosswalk_when there are no pavement markings.
Answers: 1
question
Business, 22.06.2019 14:00
Why is efficiency an important economic goal?
Answers: 2
question
Business, 22.06.2019 18:50
Plastic and steel are substitutes in the production of body panels for certain automobiles. if the price of plastic increases, with other things remaining the same, we would expect: a) the demand curve for plastic to shift to the left. b) the price of steel to fall. c) the demand curve for steel to shift to the left d) nothing to happen to steel because it is only a substitute for plastic. e) the demand curve for steel to shift to the right
Answers: 3
question
Business, 22.06.2019 19:20
Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipment six years ago was 187 and is now 194. the cost-capacity factor is 0.6. the plant engineering staff is considering a 120-kw unit of the same general design to power a small isolated plant. assume we want to add a precompressor, which (when isolated and estimated separately) currently costs $13291. determine the total cost of the 120-kw unit. (hint: skip $ and comma symbols)
Answers: 3
You know the right answer?
Thomas Textiles Corporation began November with a budget for 60,000 hours of production in the Weavi...
Questions
question
Mathematics, 11.02.2021 04:20
question
Mathematics, 11.02.2021 04:20
question
Mathematics, 11.02.2021 04:30
question
Mathematics, 11.02.2021 04:30
question
Mathematics, 11.02.2021 04:30
Questions on the website: 13722360