Business, 05.08.2020 05:01 madistupid

Pam Erickson Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2015. For tax purposes, the company employs the completed-contract method and will continue this approach in the future. (Hint: Adjust all tax consequences through the Deferred Tax Liability account.) The appropriate information related to this change is as follows. Pretax Income from:

Percentage-of-Completion Completed-Contract Difference

2014 $752,200 $586,700 $165,500
2015 683,500 444,700 238,800

(a) Assuming that the tax rate is 30%, what is the amount of net income that would be reported in 2015?

Net income $
(b) What entry(ies) are necessary to adjust the accounting records for the change in accounting principle?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 14:00
Organizational portfolio plan, the final phase of the strategic planning process, involves? a. identifying strategic business units (sbus) and establishing methods to determine how resources should be allocated among the various sbus. b. designing marketing mix strategies c. setting organizational objectives d. creating organizational strategies
Answers: 1
question
Business, 21.06.2019 15:00
Asap ! 1. evaluate the following and simplify if possible when pie = 22 11/pie = 2. evaluate the following and simplify if possible when pie = 11 and y = 5 pie/12 - y/12 = 3. evaluate the following and simplify if possible when pie = 5 : 3/pie + 2/ pie = 4. evaluate the following and simplify if possible when pie = 5 : 3/pie + 2/pie = 5. evaluate the following and simplify if possible when pie = 6 and y = 10: x/y = 6. evaluate the following and simplify if possible when pie = 6: pie/9 7. evaluate the following and simplify if possible when pie = 5 and y = 20: pie/y = 8. evaluate the following and simplify if possible when pie = 4 and y = 24: pie/y = 9. evaluate the following and simplify if possible when pie = 6 5/pie = 10. evaluate the following and simplify if possible when pie = 21 4/7 + 2/pie = 11. evaluate the following and simplify if possible when pie = 3 and y = 1 pie/10 + y/5 = 12.evaluate the following and simplify if possible when pie = 8 pie/10 =
Answers: 1
question
Business, 21.06.2019 18:30
2. high-glow currently produces 1,000 bicycles per month. the following per unit data apply for sales to regular customers: direct materials $50 direct manufacturing labor 5 variable manufacturing overhead 14 fixed manufacturing overhead 10 total manufacturing costs $79 the plant is experiencing demand shortage and is considering reducing production to 800 bicycles. what is the per unit cost of producing 800 bicycles? a) $79 per unit b) $81.50 per unit c) $74 per unit d) $69 per unit
Answers: 2
question
Business, 21.06.2019 19:00
What does the consumer price index measure? a. the change in prices of all goods and services over time b. the change in prices of specific goods and services over time c. the change in prices of final goods and services over time
Answers: 1
You know the right answer?
Pam Erickson Construction Company changed from the completed-contract to the percentage-of-completio...
Questions
question
Mathematics, 23.01.2020 19:31
Questions on the website: 13722367