Builder and Owner agree that Builder will erect a fence for Owner for $1,500. Builder claims that the fence is taking longer than Builder expected, so Owner must pay Builder $500 more or Builder will not complete the fence. Owner, needing the fence completed, agrees to the additional $500. Builder completes the fence. Owner owes Builder: . A. $1,500.
B. $2,000.
C. $1,000.
D. $1,750.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 07:30
Fill in the missing words to correctly complete each sentence about analyzing a job posting. when reviewing a job posting, it’s important to check theto determine whether it’s worth your time to apply. if the post has been up for a while or it’s already closed, move on to the next position. if it’s still available, take note of when it closes so you’ll know when you mayfrom the company in regard to an interview.
Answers: 1
question
Business, 22.06.2019 09:00
Aminor has the legal right to repudiate
Answers: 2
question
Business, 22.06.2019 09:30
When you hire an independent contractor you don't have to pay the contractors what
Answers: 3
question
Business, 22.06.2019 21:00
Roberto and reagan are both 25 percent owner/managers for bright light inc. roberto runs the retail store in sacramento, ca, and reagan runs the retail store in san francisco, ca. bright light inc. generated a $125,000 profit companywide made up of a $75,000 profit from the sacramento store, a ($25,000) loss from the san francisco store, and a combined $75,000 profit from the remaining stores. if bright light inc. is an s corporation, how much income will be allocated to roberto?
Answers: 2
You know the right answer?
Builder and Owner agree that Builder will erect a fence for Owner for $1,500. Builder claims that th...
Questions
question
Mathematics, 18.04.2020 00:41
question
Health, 18.04.2020 00:41
Questions on the website: 13722367