You are given the following data for a project: Activity Expected Time (days) Variance Critical A 15 1.25 YES B 4 2.75 NO C 10 0.75 YES D 8 1.25 YES E 6 3.25 NO F 12 1.5 YES G 7 1.25 NO H 10 1.5 YES What is the expected completion time of this project

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 14:50
Morris borrowed $9,000 from a credit union at 13% simple interest for 42 months. what were his money installment payments?
Answers: 3
question
Business, 22.06.2019 04:30
How does your household gain from specialization and comparative advantage? (what is produced, what is not produced yet paid to a specialist to produce? )
Answers: 3
question
Business, 22.06.2019 19:30
The owner of firewood to go is considering buying a hydraulic wood splitter which sells for $50,000. he figures it will cost an additional $100 per cord to purchase and split wood with this machine, while he can sell each cord of split wood for $125. if, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is expected to be 32 cords per day, what would be its efficiency?
Answers: 1
question
Business, 22.06.2019 19:40
Which term describes an alternative to car buying where monthly payments are paid for a specific period of time, after which the vehicle is returned to the dealership or bought? a. car financing b. car maintenance c. car leasing d. car ownership
Answers: 3
You know the right answer?
You are given the following data for a project: Activity Expected Time (days) Variance Critical A 15...