Following is the Project Evaluation and Review Technique (PERT) data used to execute a marketing campaign at TeaTime Inc. Calculate the variance for the project in weeks2. Activity Immediate Predecessors Duration Mean (weeks) Duration Variance (weeks2)
A 1 1
B 4 1.5
C A 3 1
D B 1 0.4
E C, D 4 1.5
F E 3 1
G F 5 1.6
a. 2.5 weeks
b. 3.0 weeks
c. 3.5 weeks
d. 4.0 weeks

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:40
Dollywood corporation accumulates the following data concerning a mixed cost, using miles as the activity level. miles driven total cost january 10,000 $16,500 february 8,000 $14,500 march 9,000 $12,500 april 7,000 $12,000 compute the variable and fixed cost elements using the high-low method
Answers: 3
question
Business, 22.06.2019 11:30
On average, someone with a bachelor's degree is estimated to earn times more than someone with a high school diploma. a)1.2 b)1.4 c)1.6 d)1.8
Answers: 1
question
Business, 22.06.2019 16:00
In microeconomics, the point at which supply and demand meet is called the blank price
Answers: 3
question
Business, 23.06.2019 02:20
Required information lansing company’s 2017 income statement and selected balance sheet data (for current assets and current liabilities) at december 31, 2016 and 2017, follow. lansing company income statement for year ended december 31, 2017 sales revenue $130,200 expenses cost of goods sold 53,000 depreciation expense 17,500 salaries expense 29,000 rent expense 10,100 insurance expense 4,900 interest expense 4,700 utilities expense 3,900 net income $7,100 lansing company selected balance sheet accounts at december 31 2017 2016 accounts receivable $6,700 $8,000 inventory 3,080 2,090 accounts payable 5,500 6,800 salaries payable 1,100 810 utilities payable 440 270 prepaid insurance 370 500 prepaid rent 440 290 required: prepare the cash flows from operating activities section only of the company’s 2017 statement of cash flows using the indirect method. (amounts to be deducted should be indicated with a minus sign.)
Answers: 1
You know the right answer?
Following is the Project Evaluation and Review Technique (PERT) data used to execute a marketing cam...
Questions
question
Physics, 20.02.2020 16:54
question
Mathematics, 20.02.2020 16:54
question
History, 20.02.2020 16:55
Questions on the website: 13722361