You wish to build a house and you have divided the process into a number of tasks, namely: B. excavation and building the foundation,
F. raising the wooden frame,
E. electrical wiring,
P. indoor plumbing,
D. dry walls and flooring,
L. landscaping.

You estimate the following duration for each of the tasks (in weeks):

Tasks B F E P D L
Duration 3 2 3 4 1 2

Some of the tasks can only be started when some other tasks are completed. For instance, you can only build the frame once the foundation has been completed, i. e. F can only start after B is completed. All the precedence constraints are summarized as follows:

• F can start only after B is completed,
• L can start only after B is completed,
• E can start only after F is completed,
• P can start only after F is completed,
• D can start only after E is completed
• D can start only after P is completed.

The goal is to schedule the starting time of each task such that the entire project is completed as soon as possible. As an example, here is a feasible schedule with a completion time of ten weeks.

Tasks B F E P D L
Starting Time 0 3 6 5 9 6
End Time 3 5 9 9 10 8

Required:
Formulate this problem as an LP. Explain your formulation. Note that there is no limit on the number of tasks that can be done in parallel. (Hint: Introduce variables to indicate the times that the tasks start.)

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 22:50
Tara incorporates her sole proprietorship, transferring it to newly formed black corporation. the assets transferred have an adjusted basis of $240,000 and a fair market value of $300,000. also transferred was $10,000 in liabilities, $1,000 of which was personal and the balance of $9,000 being business related. in return for these transfers, tara receives all of the stock in black corporation. a. black corporation has a basis of $241,000 in the property. b. black corporation has a basis of $240,000 in the property. c. tara’s basis in the black corporation stock is $241,000. d. tara’s basis in the black corporation stock is $249,000. e. none of the above.
Answers: 1
question
Business, 22.06.2019 04:10
What is the difference between secure bonds and naked bonds?
Answers: 1
question
Business, 22.06.2019 11:20
Ardmore farm and seed has an inventory dilemma. they have been selling a brand of very popular insect spray for the past year. they have never really analyzed the costs incurred from ordering and holding the inventory and currently fave a large stock of the insecticide in the warehouse. they estimate that it costs $25 to place an order, and it costs $0.25 per gallon to hold the spray. the annual requirements total 80,000 gallons for a 365 day year.a. assuming that 10,000 gallons are ordered each time an order is placed, estimate the annual inventory costs.b. calculate the eoq.c. given the eoq calculated in part b., how many orders should be placed and what is the average inventory balance? d. if it takes seven days to receive an order from suppliers, at what inventory level should ardmore place another order?
Answers: 2
question
Business, 22.06.2019 14:10
Carey company is borrowing $225,000 for one year at 9.5 percent from second intrastate bank. the bank requires a 15 percent compensating balance. the principal refers to funds the firm can effectively utilize (amount borrowed − compensating balance). a. what is the effective rate of interest? (use a 360-day year. input your answer as a percent rounded to 2 decimal places.) b. what would the effective rate be if carey were required to make 12 equal monthly payments to retire the loan?
Answers: 1
You know the right answer?
You wish to build a house and you have divided the process into a number of tasks, namely: B. excav...
Questions
question
History, 03.03.2020 16:49
question
Chemistry, 03.03.2020 16:49
question
Mathematics, 03.03.2020 16:50
question
Mathematics, 03.03.2020 16:50
Questions on the website: 13722363