AAA has a contract to build a building for $ 100,000 with an estimated time to completion of three years. A reliable cost estimate for the project is $ 60,000. In the first year of the project, AAA incurred costs totaling $ 24,000. How much profi t should AAA report at the end of the fi rst year under the percentage-of-completion method?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 23:30
Highland company produces a lightweight backpack that is popular with college students. standard variable costs relating to a single backpack are given below
Answers: 1
question
Business, 22.06.2019 05:00
Identify an organization with the low-total-cost value proposition and suggest at least two possible measures within each of the four balanced scorecard perspectives.
Answers: 3
question
Business, 22.06.2019 08:30
Blank is the internal operation that arranges information resources to support business performance and outcomes
Answers: 2
question
Business, 22.06.2019 17:40
To appeal to a new target market, the maker of hill's coffee has changed the product's package design, reformulated the coffee, begun advertising price discounts in women's magazines, and started distributing the product through gourmet coffee shops. what has been changed? a. the product's perceptual value. b.the product's 4ps. c. the method used in its target marketing. d. the ownership of the product line. e. the product's utility.
Answers: 3
You know the right answer?
AAA has a contract to build a building for $ 100,000 with an estimated time to completion of three y...
Questions
question
Mathematics, 06.05.2021 20:10
question
Mathematics, 06.05.2021 20:10
question
Mathematics, 06.05.2021 20:10
question
English, 06.05.2021 20:10
question
Mathematics, 06.05.2021 20:10
Questions on the website: 13722363