In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:.
A. To agree with the project manager.
B. To eliminate a specific risk or threat, to reduce the probability and / or impact of an adverse risk event to be within acceptable threshold limits, or to pursue an opportunity actively.
C. Not to change the project management plan to deal with a risk, or it is unable to identify any other suitable response strategy.
D. To purchase insurance, or to require performance bonds, warranties, and guarantees.
Answers: 1
Business, 21.06.2019 14:50
Morris borrowed $9,000 from a credit union at 13% simple interest for 42 months. what were his money installment payments?
Answers: 3
Business, 22.06.2019 19:00
Lucy is catering an important luncheon and wants to make sure her bisque has the perfect consistency. for her bisque to turn out right, it should have the consistency of a. cold heavy cream. b. warm milk. c. foie gras. d. thick oatmeal.
Answers: 3
Business, 22.06.2019 20:30
Before the tools that have come from computational psychiatry are ready to be used in everyday practice by psychiatrics, what is needed
Answers: 1
Business, 23.06.2019 06:30
Will mark the ! hurry ! drag and drop the ethnic group to identify the country where it is the majority. ethnic groups may be used more than once. match to the right boxcristian greeks. arabs. persiansiran qatar cyprus iraq
Answers: 1
In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates that...
Biology, 02.09.2019 23:10
Geography, 02.09.2019 23:10
Medicine, 02.09.2019 23:10
Computers and Technology, 02.09.2019 23:10