A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 09:40
Newton industries is considering a project and has developed the following estimates: unit sales = 4,800, price per unit = $67, variable cost per unit = $42, annual fixed costs = $11,900. the depreciation is $14,700 a year and the tax rate is 34 percent. what effect would an increase of $1 in the selling price have on the operating cash flow?
Answers: 2
question
Business, 22.06.2019 11:00
Zoe would like to be able to save for night courses at the local college. which of these would be a good way for zoe to make more money available for savings without dramatically changing her budget? economía
Answers: 2
question
Business, 22.06.2019 11:50
The following are the current month's balances for abc financial services, inc. before preparing the trial balance. accounts payable $ 10,000 revenue 6,000 cash 3,000 expenses 17,500 furniture 10,000 accounts receivable 14,000 common stock ? notes payable 6,500 what amount should be shown for common stock on the trial balance? a. $48.000b. $12.500c. $27.000d. $28.000
Answers: 3
question
Business, 22.06.2019 17:00
Can someone me ? i’ll mark the best answer brainliest : )
Answers: 1
You know the right answer?
A project activity has an earliest completion time of 5, an activity time of 3, and a latest complet...
Questions
question
Biology, 01.05.2021 21:00
question
Mathematics, 01.05.2021 21:00
question
Mathematics, 01.05.2021 21:00
question
History, 01.05.2021 21:10
Questions on the website: 13722361