Indiana Co. began a construction project in 2018 with a contract price of $160 million to be received when the project is completed in 2020. During 2018, Indiana incurred $39 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. A. Recognized no gross profit or loss on the project in 2018.
B. Recognized $12.37 million gross profit on the project in 2018.
C. Recognized $78.00 million loss on the project in 2018.
D. Recognized $39.00 million loss on the project in 2018.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
1. gdp is calculated by summing consumption, investment, and exports of all final goods and services produced within the borders of a given country during a specific period the dollar value of all final goods and services produced within the borders of a given country during a specific period government expenditures within the borders of a given country during a specific period the quantity of all final goods and services produced within the borders of a given country during a specific period
Answers: 3
question
Business, 22.06.2019 01:00
Which type of data is generally stored in different file formats, such as text files, spreadsheets, and so on?
Answers: 3
question
Business, 22.06.2019 11:30
Mark knopf is an auditor who has been asked to provide an audit and financial statement certification for a company that is going public on the new york stock exchange. knopf wants to know his personal liability if the company provides him with inaccurate or false information. which of the following sources of law will him answer that question? a. the city ordinances where the company headquarters is located. b. the state constitution of the state where the company is incorporated. c. code of federal regulations. d. all of the above
Answers: 1
question
Business, 22.06.2019 18:00
Carlton industries is considering a new project that they plan to price at $74.00 per unit. the variable costs are estimated at $39.22 per unit and total fixed costs are estimated at $12,085. the initial investment required is $8,000 and the project has an estimated life of 4 years. the firm requires a return of 8 percent. ignore the effect of taxes. what is the degree of operating leverage at the financial break-even level of output?
Answers: 3
You know the right answer?
Indiana Co. began a construction project in 2018 with a contract price of $160 million to be receive...
Questions
question
Mathematics, 26.01.2020 04:31
question
Mathematics, 26.01.2020 04:31
Questions on the website: 13722367