Your project to obtain charitable donations is now 34 days into a planned 44-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 28 days of the project and to bring in $25,500. Even though we are 34 days into the project, we still see that we have only 92% of this activity complete. The second activity relates to company donations and is scheduled to run for 34 days starting on day 6 and extending through day 40. We estimate that, even though we should have (28/34) 82.35% of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project. Required:
Calculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. How is the project going?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 19:00
In north korea, a farmer’s income is the same as a dentist’s income. in a country with a mixed or market economy, the difference between those two professions might be more than 5 times different. how can you explain the fact that individuals doing the same work in different countries do not earn comparable salaries?
Answers: 1
question
Business, 22.06.2019 19:50
Aproduction line has three machines a, b, and c, with reliabilities of .96, .86, and .85, respectively. the machines are arranged so that if one breaks down, the others must shut down. engineers are weighing two alternative designs for increasing the line’s reliability. plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. in either case, three machines (a, b, and c) would be used with reliabilities equal to the original three. a. compute overall system reliability under plan 1. (round your intermediate calculations and final answer to 4 decimal places.) reliability b. compute overall system reliability under plan 2. (round your intermediate calculations and final answer to 4 decimal places.) reliability c. which plan will provide the higher reliability? plan2plan1
Answers: 3
question
Business, 22.06.2019 21:20
Which of the following best explains why buying a house is more beneficial than renting? a. buying is a personal investment while renting involves giving money to the landlord. b. the monthly payments on a mortgage are generally lower than rent on an apartment. c. it's easier to sell a house than it is to get a landlord to break a rental agreement. d. housing prices can go up and down quickly in comparison to the level of rents.
Answers: 1
question
Business, 22.06.2019 22:00
Retail industry fundamentals credential exam,part 1 all answers
Answers: 3
You know the right answer?
Your project to obtain charitable donations is now 34 days into a planned 44-day project. The projec...
Questions
question
Mathematics, 18.04.2020 01:38
question
Mathematics, 18.04.2020 01:39
question
Biology, 18.04.2020 01:39
question
Biology, 18.04.2020 01:39
question
Mathematics, 18.04.2020 01:39
question
English, 18.04.2020 01:39
question
Mathematics, 18.04.2020 01:39
Questions on the website: 13722360