A manufacturer makes T-shirts in several processes. Information on the components of cycle time follow. Cutting and sewing processing 18 min. Wait time before moving 6 min. Moving shirts to ironing 8 min. Ironing T-shirts 8 min. Wait time before moving 4 min. Moving shirts to packaging 2 min. Packaging T-shirts 10 min. Quality inspection 12 min. Compute (a) value-added time, (b) inspection time, (c) move time, (d) wait time, and (e) cycle time.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:00
When is going to be why would you put money into saving account
Answers: 1
question
Business, 22.06.2019 06:30
If a team of three workers, each making the u.s. federal minimum wage, produced these 12 rugs, what would the total labor cost be? don't forget that these workers would be working overtime.
Answers: 3
question
Business, 22.06.2019 11:00
When using various forms of promotion to carry the promotion message, it is important that the recipients of the message interpret it in the same way. creating a unified promotional message, where potential customers perceive the same message, whether it is in a tv commercial, or on a billboard, or in a blog, is called
Answers: 2
question
Business, 22.06.2019 19:30
Adisadvantage of corporations is that shareholders have to pay on profits.
Answers: 1
You know the right answer?
A manufacturer makes T-shirts in several processes. Information on the components of cycle time foll...
Questions
question
Computers and Technology, 27.03.2020 18:48
Questions on the website: 13722363