A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 03:50
Suppose that a worker in agland can produce either 10 units of organic grain or 2 units of incense per year, and a worker in zenland can produce either 5 units of organic grain or 15 units of incense per year. there are 20 workers in agland and 10 workers in zenland. currently the two countries do not trade. agland produces and consumes 100 units of grain and 20 units of incense per year. zenland produces and consumes 50 units of grain and no incense per year. if each country made the decision to specialize in producing the good in which it has a comparative advantage, then the combined yearly output of the two countries would increase by a. 30 units of grain and 100 units of incense. b. 30 units of grain and 150 units of incense. c. 50 units of grain and 90 units of incense. d. 50 units of grain and 130 units of ince
Answers: 1
question
Business, 22.06.2019 12:30
land, a building and equipment are acquired for a lump sum of $ 1,000,000. the market values of the land, building and equipment are $ 300,000, $ 800,000 and $ 300,000, respectively. what is the cost assigned to the equipment? (do not round any intermediary calculations, and round your final answer to the nearest dollar.)
Answers: 1
question
Business, 23.06.2019 00:40
In 2017, "a public university was awarded a federal reimbursement grant" of $18 million to carry out research. of this, $12 million was intended to cover direct costs and $6 million to cover overhead. in a particular year, the university incurred $4 million in allowable direct costs and received $3.4 million from the federal government. it expected to incur the remaining costs and collect the remaining balance in 2018. for 2017 it should recognize revenues from the grant of
Answers: 3
question
Business, 23.06.2019 03:50
John is a journalist he went to a product demonstration for a new computer some of what he heard was informative while the rest was meant to persuade consumers to buy the product which two statements in the excerpt are persuasive rather than informative
Answers: 2
You know the right answer?
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K,...
Questions
Questions on the website: 13722367