In a work center, Machine A has a 10-minute set-up time per batch and a 2-minute per unit run time. Machine B performs the identical function but has a set-up time of 30 minutes and a 1-minute run time per unit. The work center makes products in batches ranging from 1 unit to 100 units. Assuming capacity is not a limitation on either Machine, in order to minimize the total processing time, on which batches should Machine B be used

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:30
Which of the following mechanisms would be most likely to motivate managers to act in the best interests of shareholders? a) decrease the use of restrictive covenants in bond agreements, b) take actions that reduce the possibility of a hostile takeover, c) elect a board of directors that allows managers greater freedom of action, d) increase the proportion of executive compensation that comes from stock options and reduce the proportion that is paid as cash salaries, e) eliminate a requirement that members of the board directors have a substantial investment in the firm's stocks
Answers: 2
question
Business, 22.06.2019 08:00
Suppose the number of equipment sales and service contracts that a store sold during the last six (6) months for treadmills and exercise bikes was as follows: treadmill exercise bike total sold 185 123 service contracts 67 55 the store can only sell a service contract on a new piece of equipment. of the 185 treadmills sold, 67 included a service contract and 118 did not.
Answers: 1
question
Business, 22.06.2019 16:30
Penelope summers received certain income benefits in 2018. she received $1,400 of state unemployment insurance benefits, $2,000 from a federal unemployment trust fund and $3,700 workers’ compensation received for an occupational injury. what amount of the compensation must penelope include in her income
Answers: 1
question
Business, 22.06.2019 19:00
All of the following led to the collapse of the soviet economy except a. a lack of worker incentives. c. inadequate supply of consumer goods. b. a reliance on production quotas. d. the introduction of a market economy.
Answers: 1
You know the right answer?
In a work center, Machine A has a 10-minute set-up time per batch and a 2-minute per unit run time....
Questions
question
Mathematics, 13.01.2022 04:30
question
Mathematics, 13.01.2022 04:30
question
English, 13.01.2022 04:30
question
Mathematics, 13.01.2022 04:30
question
Mathematics, 13.01.2022 04:30
question
Mathematics, 13.01.2022 04:30
question
Mathematics, 13.01.2022 04:30
Questions on the website: 13722367