Port Aransas Resort Co. (PARC) has decided to move forward with the hotel project on their property at the beach. They have selected a construction company and the project is slated to begin on June 1, 2020. PARC hopes to open the hotel before the summer season begins on May 15, 2021. The builder has given them the following list of activities related to the project and their estimated times (in weeks): ActivityImmediate PredecessorTime
A-9
B-3
C-6
DA, B, C12
EC, D15
FA9
GD, F18
HE12
a. Draw a project network
b. What are the critical activities?
c. What activity has the most slack time and how much slack does this activity have?
d. Will the project be completed by May 15, 2021?
e. If the project had uncertain/variable completion times for some of the activities and the expected completion time is 46 weeks and the variance is 6 weeks, what is the probability that the project will be completed in 48 weeks?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 18:20
Now ray has had the tires for two months and he notices that the tread has started to pull away from the tire. he has already contacted the place who sold the tires and calmly and accurately explained the problem. they didn’t him because they no longer carry that tire. so he talked with the manager and he still did not get the tire replaced. his consumer rights are being violated. pretend you are ray and write a letter to the company’s headquarters. here are some points to keep in mind when writing the letter: include your name, address, and account number, if appropriate. describe your purchase (name of product, serial numbers, date and location of purchase). state the problem and give the history of how you tried to resolve the problem. ask for a specific action. include how you can be reached.
Answers: 3
question
Business, 22.06.2019 18:30
Which of these is an example of innovation?
Answers: 2
question
Business, 22.06.2019 18:50
Retirement investment advisors, inc., has just offered you an annual interest rate of 4.4 percent until you retire in 40 years. you believe that interest rates will increase over the next year and you would be offered 5 percent per year one year from today. if you plan to deposit $13,000 into the account either this year or next year, how much more will you have when you retire if you wait one year to make your deposit?
Answers: 3
question
Business, 23.06.2019 02:00
Which of the statements is true about the values recorded in the balance sheet of a firm?
Answers: 2
You know the right answer?
Port Aransas Resort Co. (PARC) has decided to move forward with the hotel project on their property...
Questions
Questions on the website: 13722359