subject
Business, 08.04.2021 01:00 khaekhae10

Carradine Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for
the current year on total fixed manufacturing overhead cost of $105,000, variable manufacturing
overhead of $3.00 per machine-hour, and 70,000 machine-hours. The company recently
completed Job P233 which required 60 machine-hours. The amount of overhead applied to Job
P233 is closest to:
A) $90
B) $270
C) $450
D) $180

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 22:00
When slick heating company switched to an activity based costing system, it realized that it was allocating a much lower percentage of factory overhead to a product line that the marketing department was trying to push. the product line may contain which type of products?
Answers: 2
question
Business, 22.06.2019 09:00
Brian has been working for a few years now and has saved a substantial amount of money. he now wants to invest 50 percent of his savings in a bank account where it will be locked for three years and gain interest. which type of bank account should brian open? a. savings account b. money market account c. checking account d. certificate of deposit
Answers: 1
question
Business, 22.06.2019 16:30
Corrective action must be taken for a project when (a) actual progress to the planned progress shows the progress is ahead of schedule. (b) the technical specifications have been met. (c) the actual cost of the activities is less than the funds received for the work completed. (d) the actual progress is less than the planned progress.
Answers: 2
question
Business, 22.06.2019 19:10
Imagine us is a startup that offers high definition 3d prenatal ultrasounds for high-end customers. the service process includes four activities that are conducted in the sequence described below. (the time required for each activity is shown in parentheses): activity 1: welcome a patient and explain the procedure. (20 minutes)activity 2: prep the patient (e.g., show them to the room, apply ultrasound gel). (17 minutes) (*your id number represents the amount of time needed to complete this task)activity 3: take images. (5 minutes)activity 4: discuss diagnostic with patient. (20 minutes)at each location there are employees (servers) s1, s2, and s3. the assignment of tasks to servers is the following: s1 does activities 1 and 2.s2 does activity 3.s3 does activity 4.a. what is the capacity of this process (in customers per hour)? b. suppose 3 patients arrive every hour on average. ignoring any “start of day” or “end of day” effects, what are the utilizations of all three servers (%)? c. suppose each activity can be done by any server and any server can do any set of activities. however, each activity is done by only one server. for example, a possible assignment includes: s1 does activity 1, s2 does activity 2, and s3 does activities 3 and 4. of course, the original assignment of servers to activities is also feasible. what is the maximum capacity of the process (in customers per hour)? d. now consider the capacity measures in (c) and (a), what is the percentage change? why can you improve capacity without using additional resources? (there is no free lunch, right? )note: for all hw assignments, show your process of getting the results. only providing the final answers is not acceptable and will get 0%. if necessary, use a separate sheet of paper to show your work.
Answers: 3
You know the right answer?
Carradine Corporation uses a job-order costing system with a single plantwide predetermined overhea...
Questions
question
Social Studies, 27.07.2019 21:30
question
Mathematics, 27.07.2019 21:30
question
History, 27.07.2019 21:30
Questions on the website: 13722361