You are the project manager of the KMH Project. This project is slated to last eight years, You have just calculated EVM and have a CV of -83500. What type of report is needed for management?
a, Trends report
b. Exception report
c, Forecast report
d. Progress report
Clear my choice

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 23:00
James has set the goal of achieving all "a"s during this year of school.which term best describes this goal
Answers: 2
question
Business, 22.06.2019 11:20
Which stage of group development involves members introducing themselves to each other?
Answers: 3
question
Business, 22.06.2019 14:30
If a product goes up in price, and the demand for it drops, that product's demand is a. elastic b. inelastic c. stable d. fixed select the best answer from the choices provided
Answers: 1
question
Business, 22.06.2019 16:10
Regarding the results of a swot analysis, organizational weaknesses are (a) internal factors that the organization may exploit for a competitive advantage (b) internal factors that the organization needs to fix in order to be competitive (c) mbo skills that should be emphasized (d) skills and capabilities that give an industry advantages problems that a specific industry needs to correct
Answers: 1
You know the right answer?
You are the project manager of the KMH Project. This project is slated to last eight years, You have...
Questions
question
Biology, 17.09.2019 20:40
question
Business, 17.09.2019 20:40
question
Mathematics, 17.09.2019 20:40
question
Mathematics, 17.09.2019 20:40
Questions on the website: 13722363