What are the consequences to the schedule if completion of a primary task is delayed?

a. the beginnings of all related dependent tasks are also delayed.
b. time to complete the dependent task will have to be shortened.
c. the entire project schedule will be delayed.
d. the chief finance officer of the divisional office.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 16:10
Belstone, inc. is a merchandiser of stone ornaments. it sold 15,000 units during the year. the company has provided the following information: sales revenue $ 520,000 purchases (excluding freight in) 338,500 selling and administrative expenses 32,000 freight in 15,000 beginning merchandise inventory 43,000 ending merchandise inventory 58,500 how much is the gross profit for the year?
Answers: 3
question
Business, 22.06.2019 17:00
During which of the following phases of the business cycle does the real gdp fall? a. trough b. expansion c. contraction d. peak
Answers: 2
question
Business, 22.06.2019 17:30
Betty contracted with scooby’s skate store to deliver a pair of skates to jake for his birthday. scooby’s owner was going on a trip and delegated the delivery of the skates to brian. brian failed to make delivery.can jake sue brian for breach of contract, as he was not a party to the original contract? explain your answer. brian was not a party to the original contract. why would a court hold him responsible for failing to make delivery? if you do not think a court would hold him responsible, explain your answer. can jake sue scooby’s skates for breach of contract? explain your answer.
Answers: 2
question
Business, 22.06.2019 17:50
Variable rate cd’s = $90 treasury bills = $150 discount loans = $20 treasury notes = $100 fixed rate cds = $160 money market deposit accts. = $140 savings deposits = $90 fed funds borrowing = $40 variable rate mortgage loans $140 demand deposits = $40 primary reserves = $50 fixed rate loans = $210 fed funds lending = $50 equity capital = $120 a. develop a balance sheet from the above data. be sure to divide your balance sheet into rate-sensitive assets and liabilities as we did in class and in the examples. b. perform a standard gap analysis and a duration analysis using the above data if you have a 1.15% decrease in interest rates and an average duration of assets of 5.4 years and an average duration of liabilities of 3.8 years. c. indicate if this bank will remain solvent after the valuation changes. if so, indicate the new level of equity capital after the valuation changes. if not, indicate the amount of the shortage in equity capital.
Answers: 3
You know the right answer?
What are the consequences to the schedule if completion of a primary task is delayed?

a...
Questions
question
Mathematics, 27.08.2019 08:30
question
Mathematics, 27.08.2019 08:30
Questions on the website: 13722361