Critical Path Method (CPM) with Crashing The film The Lord of the Rings: The Return of the King, the last installment of The Lord of the Rings trilogy, was directed by Peter Jackson and released on December 17 2003 in the U. S. with huge success. Eventually, the film won 11 Oscars for all of its nominations. The film's box office has been more than $1 billion. In the film, there are long sequences in which not all main characters appear at the same time. And there are big scenes where everybody shows up. Thinking about the making of the film, behind the scenes, we can hypothetically break down the entire cinematic project into the following aggregate activities (We assume away all the complexities in shooting the three installments at the same time and other production details):
‐ Plan, screenplay, finance, cast, film crew, location
‐ Construction of movie sets
‐ Shooting sequence 1
‐ Shooting sequence 2
‐ Shooting sequence 3
‐ Big scene sequence
‐ Post‐production & finalization before release
We have the following hypothetical data on time in months and cost in millions of dollars:
ID IP T ES EF LS LF SLK NT NC CT CC CCR
A ‐ 6.0 6.0 13.0 6.0 13.0
B A 4.0 4.0 9.0 3.0 12.0
C B 4.0 4.0 12.0 4.0 12.0
D B 5.0 11.0 5.0 14.0 4.0 16.0
E B 6.0 0.0 6.0 16.0 4.0 19.0
F C, D,E 4.0 4.0 19.0 4.0 19.0
G F 6.0 6.0 11.0 5.0 13.5
Note: IP = Immediate Predecessor; T = NT = Normal Time; ES = Earliest Start; EF = Earliest Finish; LS = Latest Start; LF = Latest Finish; SLK = Slack Time; NT = Normal Time; NC = Normal
Cost; CT = Crash Time; CC = Crash Cost; & CCR = Crash Cost/Time Unit (Crash Cost Rate).
Copy the table to your homework and complete the following parts:
By looking at the chart in part (a), find all possible paths through the network with their corresponding path times. Based on these path times, determine the critical path.
Based on part (a) By using the forward and backward passes together with the four time determination rules, fill your calculations for ES,
EF, LS, LF, and SLK in the appropriate cells.
(b) Try to independently fill in the columns ES, EF, LS, LF, and SLK of the table. If you have difficulties, refer to part (a). Determine the activity with the most slack time.
c) Based on part (a), find the critical path by going through the activities with no slack time.
Compare this result with the critical path found in part (b).
d) Use appropriate data to compute crash costs per time unit and fill in the CCR column. Cross out any CCR cells where the corresponding activities cannot be crashed.
(e) Find the total normal cost of the film. Find the normal cost on the original critical path. Compute the cost proportion of the critical path in the film's budget.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 07:10
mark, a civil engineer, entered into a contract with david. as per the contract, mark agreed to design and build a house for david for a specified fee. mark provided david with an estimation of the total cost and the contract was mutually agreed upon. however, during construction, when mark increased the price due to a miscalculation on his part, david refused to pay the amount. this scenario is an example of a mistake.
Answers: 1
question
Business, 22.06.2019 07:50
Budget in this final week, you will develop a proposed budget of $150,000 for the first year of the program and complete the final concept paper for the proposed program due for senior management review. the budget should identify the program's anticipated expenses for the year ahead. budget line items should be consistent with the proposed program and staffing plan. using the readings for the week, the south university online library, and the internet, complete the following tasks: create a proposed budget of $150,000 for the first year of the proposed program including the cost for personnel, supplies, education materials, marketing costs, and so on in a microsoft excel spreadsheet. you may transfer your budget to your report. justify the cost for each item of the proposed budget in a budget narrative.
Answers: 2
question
Business, 22.06.2019 19:00
In 1975, mcdonald’s introduced its egg mcmuffin breakfast sandwich, which remains popular and profitable today. this longevity illustrates the idea of:
Answers: 1
question
Business, 22.06.2019 19:10
Pam is a low-risk careful driver and fran is a high-risk aggressive driver. to reveal their driver types, an auto-insurance company a. refuses to insure high-risk drivers b. charges a higher premium to owners of newer cars than to owners of older cars c. offers policies that enable drivers to reveal their private information d. uses a pooling equilibrium e. requires drivers to categorize themselves as high-risk or low-risk on the application form
Answers: 3
You know the right answer?
Critical Path Method (CPM) with Crashing The film The Lord of the Rings: The Return of the King, t...
Questions
Questions on the website: 13722359