According to Walter Shewhart: a) chance causes should be eliminated whenever possible
b) assignable causes could be ignored if they did not cause too much variation
c) the mean, uppercontrollimit, lower controllimit and warning lines that are two sigma from the mean are indicated by horizontal lines in the control chart
d) chance causes could be fixed
e) a control chart has time on the top axis and a plot of sample measurements

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:10
Your team has identified the risks on the project and determined their risk score. the team is in the midst of determining what strategies to put in place should the risks occur. after some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. which of the following is true regarding this question? a. this is a positive response strategy.b. this is a negative response strategy.c. this is a response strategy for either positive or negative risk known as contingency planning.d. this is a response strategy for either positive or negative risks known as passive acceptance.
Answers: 2
question
Business, 22.06.2019 17:40
Turrubiates corporation makes a product that uses a material with the following standards standard quantity 8.0 liters per unit standard price $2.50 per liter standard cost $20.00 per unit the company budgeted for production of 3,800 units in april, but actual production was 3,900 units. the company used 32,000 liters of direct material to produce this output. the company purchased 20,100 liters of the direct material at $2.6 per liter. the direct materials purchases variance is computed when the materials are purchased. the materials quantity variance for april is:
Answers: 1
question
Business, 22.06.2019 20:30
Hank itzek manufactures and sells homemade wine, and he wants to develop a standard cost per gallon. the following are required for production of a 70-gallon batch. 2,700 ounces of grape concentrate at $0.04 per ounce 77 pounds of granulated sugar at $0.43 per pound 133 lemons at $0.79 each 350 yeast tablets at $0.24 each 350 nutrient tablets at $0.14 each 2,500 ounces of water at $0.001 per ounce hank estimates that 4% of the grape concentrate is wasted, 9% of the sugar is lost, and 32% of the lemons cannot be used. compute the standard cost of the ingredients for one gallon of wine. (round intermediate calculations and final answer to 2 decimal places, e.g.
Answers: 3
question
Business, 22.06.2019 20:30
What talent or skill do u wish too develop for yourself
Answers: 1
You know the right answer?
According to Walter Shewhart: a) chance causes should be eliminated whenever possible
b) ass...
Questions
Questions on the website: 13722367