A hospitality company is evaluating building a new hotel in Bloomington (capital project) that management forecasts will generate $45,000 each year over its six (6) year life. If the required rate of return given the project's identified risks is 12% (percent), and the project's up front costs are estimated at $165,000, should management go forward with the project? a. Management should approve the new hotel since the project's NPV is positive.
b. Management should reject the new hotel project as the project's NPV is negative.
c. Unable to determine given information.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:00
Which is not an example of a cyclical company? a) airlines b) hotel industry c) medical d) theme parks
Answers: 1
question
Business, 22.06.2019 21:00
Mr. beautiful, an organization that sells weight training sets, has an ordering cost of $40 for the bb-1 set. (bb-1 stands for body beautiful number 1.) the carrying cost for bb-1 is $5 per set per year. to meet demand, mr. beautiful orders large quantities of bb-1 seven times a year. the stockout cost for bb-1 is estimated to be $50 per set. over the past several years, mr. beautiful has observed the following demand during the lead time for bb-1: demand during lead time probability40 0.150 0.260 0.270 0.280 0.290 0.1total 1.0the reorder point for bb-1 is 60 sets. what level of safety stock should be maintained for bb-1?
Answers: 3
question
Business, 22.06.2019 22:00
What resourse is both renewable and inexpensive? gold coal lumber mineral
Answers: 1
question
Business, 23.06.2019 05:30
What is a potential negative effect of an expansionary policy? decreased borrowing increased interest rates increased inflation decreased available credit
Answers: 1
You know the right answer?
A hospitality company is evaluating building a new hotel in Bloomington (capital project) that manag...
Questions
question
Mathematics, 29.01.2020 13:00
Questions on the website: 13722367