Given the following assumptions, develop a cost estimate (Labor only) that integrates all of the cost elements into a final bid price to the customer. What is the total cost for the project? How long will the project take to complete? Function points in the project: 252
Software engineers assigned to this team: 5
Function point productivity per software engineer: 5 per month
Workdays per typical month: 22
Productivity hours per typical workday: 8
Gross Hourly wage rate per software engineer (does not include fringe benefits): 50
Overhead (fringe benefit, other direct overhead) rate: 40%
G&A rate: 11.5%
Proposed Profit: 15%

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:30
Why does the united states government provide tax breaks related to the amount of money companies spend on research and development? a. to provide incentives for companies to conduct research and development to allow antitrust authorities b. to challenge joint research efforts c. to protect the right of inventors d. to produce and sell their inventions e. to involve less government scrutiny than a government funded project
Answers: 1
question
Business, 22.06.2019 05:00
One question from a survey was "how many credit cards do you currently have? " the results of the survey are provided. complete parts (a) through (g) below. click the icon to view the survey results. (a) determine the mean number of credit cards based on the raw data. the mean is 3.113.11 credit cards. (type an integer or a decimal. do not round.) (b) determine the standard deviation number of credit cards based on the raw data. the standard deviation is 1.9111.911 credit cards. (round to three decimal places as needed.) (c) determine a probability distribution for the random variable, x, the number of credit cards issued to an individual. x (# of cards) p(x) x (# of cards) p(x) 1 0.280.28 6 nothing 2 nothing 7 nothing 3 nothing 8 nothing 4 nothing 9 nothing 5 nothing 10 nothing (type integers or decimals. do not round.)
Answers: 2
question
Business, 22.06.2019 08:40
Calculate the cost of each capital component—in other words, the after-tax cost of debt, the cost of preferred stock (including flotation costs), and the cost of equity (ignoring flotation costs). use both the capm method and the dividend growth approach to find the cost of equity.calculate the cost of new stock using the dividend growth approach.what is the cost of new common stock based on the capm? (hint: find the difference between re and rs as determined by the dividend growth approach and then add that difference to the capm value for rs.)assuming that gao will not issue new equity and will continue to use the same target capital structure, what is the company’s wacc? e. suppose gao is evaluating three projects with the following characteristics.each project has a cost of $1 million. they will all be financed using the target mix of long-term debt, preferred stock, and common equity. the cost of the common equity for each project should be based on the beta estimated for the project. all equity will come from reinvested earnings.equity invested in project a would have a beta of 0.5 and an expected return of 9.0%.equity invested in project b would have a beta of 1.0 and an expected return of 10.0%.equity invested in project c would have a beta of 2.0 and an expected return of 11.0%.analyze the company’s situation, and explain why each project should be accepted or rejected g
Answers: 1
question
Business, 22.06.2019 12:50
Performance bicycle company makes steel and titanium handle bars for bicycles. it requires approximately 1 hour of labor to make one handle bar of either type. during the most recent accounting period, barr company made 7,700 steel bars and 2,300 titanium bars. setup costs amounted to $35,000. one batch of each type of bar was run each month. if a single company-wide overhead rate based on direct labor hours is used to allocate overhead costs to the two products, the amount of setup cost assigned to the steel bars will be:
Answers: 2
You know the right answer?
Given the following assumptions, develop a cost estimate (Labor only) that integrates all of the cos...
Questions
question
History, 08.02.2021 20:20
question
Mathematics, 08.02.2021 20:20
question
History, 08.02.2021 20:20
question
English, 08.02.2021 20:20
Questions on the website: 13722363