A) Given the following Master Schedule, fill in the Projected Available and Available to Promise rows: On Hand: 35Planning Time Fence: 10Lot Size: 200
Demand Time Fence: 2
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 30 40 40 50 40 40 30 40 40 50 40 40
Customer Orders 31 35 29 21 17 14 33 11 52 0 1
Projected Avail.
Avail. To Promise
MPS 200 200
b) A customer wants an order of 100 in period 4. What can you tell them?
c) The customer from part (b) cancels their request, but then says they want 120 in period 5. What do you tell them now?
d) Sales has requested that you add a MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?
e) What action (if any) should be taken in period 11? Why is it okay to take the action?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 13:30
Yard tools manufactures lawnmowers, weed-trimmers, and chainsaws. its sales mix and unit contribution margin are as follows. sales mix unit contribution margin lawnmowers 20 % $30 weed-trimmers 50 % $20 chainsaws 30 % $40 yard tools has fixed costs of $4,200,000. compute the number of units of each product that yard tools must sell in order to break even under this product mix.
Answers: 3
question
Business, 22.06.2019 14:40
You are purchasing a bond that currently sold for $985.63. it has the time-to-maturity of 10 years and a coupon rate of 6%, paid semi-annually. the bond can be called for $1,020 in 3 years. what is the yield to maturity of this bond?
Answers: 2
question
Business, 22.06.2019 18:30
Amanufacturer has paid an engineering firm $200,000 to design a new plant, and it will cost another $2 million to build the plant. in the meantime, however, the manufacturer has learned of a foreign company that offers to build an equivalent plant for $2,100,000. what should the manufacturer do?
Answers: 1
question
Business, 23.06.2019 03:00
What are the uses of national income data
Answers: 1
You know the right answer?
A) Given the following Master Schedule, fill in the Projected Available and Available to Promise row...
Questions
question
Mathematics, 05.11.2020 19:30
question
Mathematics, 05.11.2020 19:30
question
Mathematics, 05.11.2020 19:30
question
Physics, 05.11.2020 19:30
question
Mathematics, 05.11.2020 19:30
question
Mathematics, 05.11.2020 19:30
Questions on the website: 13722360