Project Management Practice ProblemBragg’s Bakery is building a new automated bakery downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed. TIME (WEEK)CRASH TIME (WEEK)EXPEDITING COST/WEEKA-963000BA853500CA15104000 DB, C532000EC1062500FD, E215000
Hint: I have directly provided the crashing cost per unit time.
a. What is the normal project length?
b. What is the critical path in this project?
c. Which activity will you choose to crash first to reduce the duration of the project by one week?
d. What is the project length if all activities are crashed to their minimum?
e. What is the slack for activity D?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 02:10
The federal reserve's organization while all members of the federal reserve board of governors vote at federal open market committee (fomc) meetings, only of the regional bank presidents are members of the fomc. the federal reserve's role as a lender of last resort involves lending to which of the following financially troubled institutions? u.s. banks that cannot borrow elsewhere governments in developing countries during currency crises u.s. state governments when they run short on tax revenues the federal reserve's primary tool for changing the money supply is . in order to decrease the number of dollars in the u.s. economy (the money supply), the federal reserve will government bonds.
Answers: 1
question
Business, 22.06.2019 11:20
Lusk corporation produces and sells 14,300 units of product x each month. the selling price of product x is $25 per unit, and variable expenses are $19 per unit. a study has been made concerning whether product x should be discontinued. the study shows that $72,000 of the $102,000 in monthly fixed expenses charged to product x would not be avoidable even if the product was discontinued. if product x is discontinued, the annual financial advantage (disadvantage) for the company of eliminating this product should be:
Answers: 1
question
Business, 22.06.2019 13:40
Salge inc. bases its manufacturing overhead budget on budgeted direct labor-hours. the variable overhead rate is $8.10 per direct labor-hour. the company's budgeted fixed manufacturing overhead is $74,730 per month, which includes depreciation of $20,670. all other fixed manufacturing overhead costs represent current cash flows. the direct labor budget indicates that 5,300 direct labor-hours will be required in september. the company recomputes its predetermined overhead rate every month. the predetermined overhead rate for september should be:
Answers: 3
question
Business, 22.06.2019 20:20
Xinhong company is considering replacing one of its manufacturing machines. the machine has a book value of $39,000 and a remaining useful life of 5 years, at which time its salvage value will be zero. it has a current market value of $49,000. variable manufacturing costs are $33,300 per year for this machine. information on two alternative replacement machines follows. alternative a alternative b cost $ 115,000 $ 117,000 variable manufacturing costs per year 22,900 10,100 1. calculate the total change in net income if alternative a and b is adopted. 2. should xinhong keep or replace its manufacturing machine
Answers: 1
You know the right answer?
Project Management Practice ProblemBragg’s Bakery is building a new automated bakery downtown Sandus...
Questions
question
Mathematics, 06.02.2021 08:50
question
History, 06.02.2021 08:50
question
Mathematics, 06.02.2021 08:50
Questions on the website: 13722362