Business, 05.07.2021 20:00 japerson

Sheffield Corp. has a materials price standard of $2.00 per pound. 4900 pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 4900 pounds, although the standard quantity allowed for the output was 4000 pounds. Sheffield Corp.'s materials quantity variance is:. a. $1980 U.
b. $1800 F.
c. $1800 U.
d. $1980 F.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 15:30
Which of the following statements accurately describes how costs and benefits are calculated?
Answers: 1
question
Business, 21.06.2019 18:10
In a sumif conditional function, what should be the order of terms in the parentheses?
Answers: 1
question
Business, 21.06.2019 22:00
The market yield on spice grills' bonds is 15%, and the firm's marginal tax rate is 33%. what is their shareholders' required return if the equity risk premium is 4%?
Answers: 1
question
Business, 22.06.2019 07:30
Most states have licensing registration requirements for child care centers and family daycare homes. these usually include minimum standard for operation. which of the following would you most likely find required in a statement of state licensing standards for child care centers?
Answers: 2
You know the right answer?
Sheffield Corp. has a materials price standard of $2.00 per pound. 4900 pounds of materials were pur...
Questions
question
Social Studies, 26.12.2020 16:30
question
Chemistry, 26.12.2020 16:30
question
English, 26.12.2020 16:40
Questions on the website: 13722360