Riverbed Corp. enters into a contract with a customer to build an apartment building for $1,013,300. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $152,100 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $50,700 each week that completion is delayed. Riverbed commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability
August 1, 2021 70%
August 8, 2021 20
August 15, 2021 5
After August 15, 2021 5

Required:
Determine the transaction price for this contract.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 19:00
By 2020, automobile market analysts expect that the demand for electric autos will increase as buyers become more familiar with the technology. however, the costs of producing electric autos may increase because of higher costs for inputs (e.g., rare earth elements), or they may decrease as the manufacturers learn better assembly methods (i.e., learning by doing). what is the expected impact of these changes on the equilibrium price and quantity for electric autos?
Answers: 1
question
Business, 22.06.2019 19:30
Problem page a medical equipment industry manufactures x-ray machines. the unit cost c (the cost in dollars to make each x-ray machine) depends on the number of machines made. if x machines are made, then the unit cost is given by the function =cx+−0.3x2126x31,935 . how many machines must be made to minimize the unit cost?
Answers: 3
question
Business, 22.06.2019 19:40
Your father's employer was just acquired, and he was given a severance payment of $375,000, which he invested at a 7.5% annual rate. he now plans to retire, and he wants to withdraw $35,000 at the end of each year, starting at the end of this year. how many years will it take to exhaust his funds, i.e., run the account down to zero? a. 22.50 b. 23.63 c. 24.81 d. 26.05 e. 27.35
Answers: 2
question
Business, 22.06.2019 20:20
Direct materials (4.2 x $15) $ 63direct labor ($12 x 17.5) $210manufacturing overhead ($2.40 x 17.5) $42total job cost $ 315dougan, inc. allocates overhead based on a predetermined overhead rate of $2.40 per direct labor hour. employees are paid $12.00 per hour. job 24 requires 4.2 pounds of direct materials at a cost of $15.00 per pound. employees worked a total of 17.5 hours to complete the job. actual manufacturing overhead costs totaled $80,000 for the year for the company. how much is the cost of job 24?
Answers: 1
You know the right answer?
Riverbed Corp. enters into a contract with a customer to build an apartment building for $1,013,300....
Questions
question
Mathematics, 15.01.2021 22:20
question
Mathematics, 15.01.2021 22:20
question
Mathematics, 15.01.2021 22:20
question
Mathematics, 15.01.2021 22:20
Questions on the website: 13722367