Job Order Days Waiting Process Time Due Date Start Finish Flow Time Late Cheng third 5 15 12 Allison second 6 2 14 Hepner first 7 17 20 Noel sixth 2 12 33 Dickson fifth 3 13 47 Miller fourth 4 8 69 Bahouth seventh 1 16 88 A. If these jobs have already been sequenced what method was used

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 23:30
Which type of market are you in if your company, along with three other companies, controls 95 percent of the total music industry?
Answers: 3
question
Business, 22.06.2019 17:40
Aproduct has a demand of 4000 units per year. ordering cost is $20, and holding cost is $4 per unit per year. the cost-minimizing solution for this product is to order: ? a. 200 units per order. b. all 4000 units at one time. c. every 20 days. d. 10 times per year. e. none of the above
Answers: 3
question
Business, 22.06.2019 19:00
In north korea, a farmer’s income is the same as a dentist’s income. in a country with a mixed or market economy, the difference between those two professions might be more than 5 times different. how can you explain the fact that individuals doing the same work in different countries do not earn comparable salaries?
Answers: 1
question
Business, 22.06.2019 19:40
Lauer corporation uses the periodic inventory system and has provided the following information about one of its laptop computers: date transaction number of units cost per unit 1/1 beginning inventory 210 $ 910 5/5 purchase 310 $ 1,010 8/10 purchase 410 $ 1,110 10/15 purchase 255 $ 1,160 during the year, lauer sold 1,025 laptop computers. what was cost of goods sold using the lifo cost flow assumption?
Answers: 1
You know the right answer?
Job Order Days Waiting Process Time Due Date Start Finish Flow Time Late Cheng third 5 15 12 Allison...
Questions
question
Mathematics, 30.01.2020 04:53
question
Biology, 30.01.2020 04:53
question
Mathematics, 30.01.2020 04:53
Questions on the website: 13722367