Business, 03.08.2021 04:00 michellemitchel

K. Nelson, project manager of Print... K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software
ID Description Predecessor Time
(days)
A External specifications None 8
B Review design features A 2
C Document new features A 3
D Write software A 60
E Program and test B 40
F Edit and publish notes C 2
G Review manual D 2
H Alpha site E, F 20
I Print manual G 10
J Beta site H, I 10
K Manufacture J 12
L Release and ship K 3
The project is expected to take days
The critical path is
Early Start on activity E is:
Late finish on activity F is:
Slack for activity C is:

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 13:00
Reliability and validity reliability and validity are two important considerations that must be made with any type of data collection. reliability refers to the ability to consistently produce a given result. in the context of psychological research, this would mean that any instruments or tools used to collect data do so in consistent, reproducible ways. unfortunately, being consistent in measurement does not necessarily mean that you have measured something correctly. to illustrate this concept, consider a kitchen scale that would be used to measure the weight of cereal that you eat in the morning. if the scale is not properly calibrated, it may consistently under- or overestimate the amount of cereal that’s being measured. while the scale is highly reliable in producing consistent results (e.g., the same amount of cereal poured onto the scale produces the same reading each time), those results are incorrect. this is where validity comes into play. validity refers to the extent to which a given instrument or tool accurately measures what it’s supposed to measure. while any valid measure is by necessity reliable, the reverse is not necessarily true. researchers strive to use instruments that are both highly reliable and valid.
Answers: 1
question
Business, 22.06.2019 21:40
Western electric has 32,000 shares of common stock outstanding at a price per share of $79 and a rate of return of 13.00 percent. the firm has 7,300 shares of 7.80 percent preferred stock outstanding at a price of $95.00 per share. the preferred stock has a par value of $100. the outstanding debt has a total face value of $404,000 and currently sells for 111 percent of face. the yield to maturity on the debt is 8.08 percent. what is the firm's weighted average cost of capital if the tax rate is 39 percent?
Answers: 2
question
Business, 23.06.2019 09:10
How can a company salesperson with product development
Answers: 3
question
Business, 23.06.2019 12:30
30 points + mark as the brainliest use the internet to research legal concerns that could result from increased use of technology in business. discuss some of these concerns.
Answers: 3
You know the right answer?
K. Nelson, project manager of Print... K. Nelson, project manager of Print Software, Inc., wants yo...
Questions
question
History, 01.04.2020 20:23
Questions on the website: 13722363