A project has seven activities: A. B, C, D, E, F, and G. Activities A. B, and D can start anytime. Activity A takes 3 weeks. Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. What is the critical path

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 23:50
Juan has a retail business selling skateboard supplies he maintains large stockpiles of every item he sells in a warehouse on the outskirts of town he keeps finding that he has to reorder certain supplies all the time but others only once a year how can he solve this problem?
Answers: 1
question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 04:00
Burberry is pursuing a focused differentiation strategy aimed at high-end luxury customers. however, the company is also employing a segmentation strategy to separate customers within that focus. the strategy offers items at an entry-level price point for customers who desire to be like celebrities such as sarah jessica parker as well as couture items for those richest and celebrity customers. what strategy is burberry pursuing?
Answers: 3
question
Business, 22.06.2019 09:50
Acar manufacturer uses new machines that automatically assemble an engine from parts fed to the system. the machine can regulate the speed ofassembly depending on the number of parts produced. which type of technology does this machine use? angenoem mense wat ons in matin en esta va ser elthe machine uses
Answers: 3
You know the right answer?
A project has seven activities: A. B, C, D, E, F, and G. Activities A. B, and D can start anytime. A...
Questions
question
Mathematics, 01.12.2021 02:40
Questions on the website: 13722363