Cooper Construction Company had a contract starting April 2020, to construct a $24,000,000 building that is expected to be completed in September 2022, at an estimated cost of $22,000,000. At the end of 2020, the costs to date were $10,120,000 and the estimated total costs to complete had not changed. The progress billings during 2020 were $4,800,000 and the cash collected during 2020 was 3,200,000. Cooper uses the percentage-of-completion method. For the year ended December 31, 2021, Cooper would recognize gross profit on the building of:

a. $843,333
b. $920,000
c. $1,080,000
d. $0

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 15:00
Which energy career pathways work with renewable energy? check all that apply.
Answers: 1
question
Business, 23.06.2019 16:30
Circuittown commenced a gift card program in january 2018 and sold $12,150 of gift cards in january, $19,150 in february, and $18,100 in march of 2018 before discontinuing further gift card sales. during 2018, gift card redemptions were $7,850 for the january gift cards sold, $4,350 for the february cards, and $4,250 for the march cards. circuittown considers gift cards to be “broken” (not redeemable) 10 months after sale. required: 1. how much revenue will circuittown recognize with respect to january gift card sales during 2018? 2. prepare journal entries to record the sale of january gift cards, redemption of gift cards (ignore sales tax), and breakage (expiration) of gift cards. 3. how much revenue will circuittown recognize with respect to march gift card sales during 2018? 4. what liability for deferred revenue associated with gift card sales would circuittown show as of december 31, 2018?
Answers: 2
question
Business, 23.06.2019 19:50
Describe a situation when you used a text reference successfully to preview, prepare for, review or locate information you were learning.
Answers: 2
question
Business, 23.06.2019 21:30
The first step of a literature review includes the identification of the various unpublished and published materials that are available on the topic of interest, and gaining access to these. discuss at least three different data sources that charles could use and explain how charles will benefit from using these specific data sources
Answers: 3
You know the right answer?
Cooper Construction Company had a contract starting April 2020, to construct a $24,000,000 building...
Questions
Questions on the website: 13722360