Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days, but most likely will require 20 days. What is the 20 day estimate called

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 17:50
On january 1, eastern college received $1,350,000 from its students for the spring semester that it recorded in unearned tuition and fees. the term spans four months beginning on january 2 and the college spreads the revenue evenly over the months of the term. assuming the college prepares adjustments monthly, what amount of tuition revenue should the college recognize on february 28?
Answers: 2
question
Business, 22.06.2019 18:00
Martha entered into a contract with terry, an art dealer. according to the contract, terry was to supply 18 th century artifacts to martha for the play she was directing, and martha was ready to pay $50,000 for this. another director needed the same artifacts and was ready to pay $60,000. terry decided not to sell the artifacts to martha. in this case, the court may order terry to:
Answers: 2
question
Business, 22.06.2019 20:40
Financial performance is measured in many ways. requirements 1. explain the difference between lag and lead indicators. 2. the following is a list of financial measures. indicate whether each is a lag or lead indicator: a. income statement shows net income of $100,000 b. listing of next week's orders of $50,000 c. trend showing that average hits on the redesigned website are increasing at 5% per week d. price sheet from vendor reflecting that cost per pound of sugar for the next month is $2 e. contract signed last month with large retail store that guarantees a minimum shelf space for grandpa's overloaded chocolate cookies for the next year
Answers: 2
question
Business, 23.06.2019 08:40
Suppose a movie theater determines it can charge different prices to patrons who go to weekday matinees and people who attend evening and weekend shows . the movie theater's goal is to increase total revenue. the price elasticity of demand for weekend and evening patrons is -0.40, and the price elasticity of demand for matinee moviegoers is -1.90. based on the price elasticity of demand for each group of people, how should the movie theater adjust its prices?
Answers: 3
You know the right answer?
Mauricio estimates that the first module of the project could be completed in as few as 15 days or c...
Questions
question
Mathematics, 12.12.2020 16:20
Questions on the website: 13722367