A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70 percent complete. The planners were expecting to be only 56 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,425,000 and it was done for only $1,305,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,505,000 but was actually done for $9,005,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,505,000. To date they have spent $5,005,000 on the superstructure. Schedule variance
Schedule performance index
Cost performance index

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:30
marketing strategies should be established before marketing objectives are decided. t/f
Answers: 1
question
Business, 22.06.2019 04:40
Select the correct text in the passage.which sentences in the given passage explains the limitations of monetary policies? monetary policies - limitationsmonetary policies are set by the central bank to bring about growth in the economy.de can be achieved these policiesw at anden i sca poit would be fair to say that changes in the economy cannot be brought about instantly by monetary po des.monetary policy can only influence not control, economic growththe monetary policy makers do work on sining the perfect balance between demand and supply of money in the economy
Answers: 3
question
Business, 22.06.2019 07:30
Jordan, inc. sells fireworks. the company’s marketing director developed the following cost of goods sold budget for april, may, june, and july. april may june july budgeted cost of goods sold $62,000 $72,000 $82,000 $88,000 jordan had a beginning inventory balance of $3,000 on april 1 and a beginning balance in accounts payable of $14,600. the company desires to maintain an ending inventory balance equal to 15 percent of the next period’s cost of goods sold. jordan makes all purchases on account. the company pays 65 percent of accounts payable in the month of purchase and the remaining 35 percent in the month following purchase. required prepare an inventory purchases budget for april, may, and june. determine the amount of ending inventory jordan will report on the end-of-quarter pro forma balance sheet. prepare a schedule of cash payments for inventory for april, may, and june. determine the balance in accounts payable jordan will report on the end-of-quarter pro forma balance sheet.
Answers: 2
question
Business, 22.06.2019 16:50
According to ceo heidi ganahl, camp bow wow requires a strong and consistent corporate culture to keep all local franchise owners "on the same page" and to follow a common template for the business and brand. this culture could become detrimental over time because: (a) strong consistent cultures are inflexible and incapable of adapting to environmental change (b) strong consistent cultures are too flexible and capable of adapting to environmental change (c) strong consistent cultures don’t perform well in any environment (d) the passing of time provides stability and predictability for businesses
Answers: 2
You know the right answer?
A project to build a new bridge seems to be going very well since the project is well ahead of sched...
Questions
question
History, 05.10.2019 03:00
question
Mathematics, 05.10.2019 03:00
Questions on the website: 13722367