The term describes a product produced as part of a project. a. deliverable b. scope c. variance d. work package

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 01:50
Which value describes the desire to be one’s own boss? a. autonomy b. status c. security d. entrepreneurship
Answers: 2
question
Business, 22.06.2019 19:10
Greenway industries is a major multinational conglomerate. its business units compete in a range of industries, including home appliances, pharmaceuticals, commercial real estate, and plastics manufacturing. although its largest business unit, which produces kitchen appliances, is among the most profitable in the industry, it generates only 35 percent of the company's revenues. which of the following is most likely true of greenway's stock price? a. it is valued at less than the sum of its individual business units. b. it is valued at greater than the sum of individual business units. c. it is valued at the exact sum of individual business units. d. it is consistently lower than the industry average.it is valued at greater than the sum of individual business units.
Answers: 1
question
Business, 22.06.2019 21:10
Which of the following statements is (are) true? i. free entry to a perfectly competitive industry results in the industry's firms earning zero economic profit in the long run, except for the most efficient producers, who may earn economic rent. ii. in a perfectly competitive market, long-run equilibrium is characterized by lmc < p < latc. iii. if a competitive industry is in long-run equilibrium, a decrease in demand causes firms to earn negative profit because the market price will fall below average total cost.
Answers: 3
question
Business, 22.06.2019 23:00
Which of the following is not one of the four principles of bottleneck management? a. increasing capacity at non-bottleneck stations is a mirageb. lost time at the bottleneck is lost system capacity.c. release work orders to the system at the bottleneck's capacity pace.d. increased bottleneck capacity is increased system capacity.e. bottlenecks should be moved to the end of the system process.
Answers: 1
You know the right answer?
The term describes a product produced as part of a project. a. deliverable b. scope c. variance d....
Questions
question
Mathematics, 06.10.2021 06:40
question
Mathematics, 06.10.2021 06:40
question
Mathematics, 06.10.2021 06:50
question
Mathematics, 06.10.2021 07:00
Questions on the website: 13722367