All of the following statements correctly describe a contemporary approach to create the work breakdown structure (wbs) for a project except:
a. project teams may use a template or a wbs from a previous project as a starting point.
b. project teams may jump start the wbs construction with a brainstorming session.
c. project teams may adopt a top-down approach to construct the wbs.
d. project teams may rely upon the project manager to create all levels of the wbs.

ansver
Answers: 3

Another question on Chemistry

question
Chemistry, 22.06.2019 06:30
What is the polyatamic ion of borate
Answers: 1
question
Chemistry, 22.06.2019 11:40
Enzymes affect the reactions in living cells by changing the
Answers: 3
question
Chemistry, 22.06.2019 13:00
The number of neutrons is equal to the atomic number minus the atomic mass. a. true b. false
Answers: 2
question
Chemistry, 22.06.2019 20:00
If one fission reaction of a uranium-235 atom produced two neutrons, how many neutrons would be released if the chain reaction occurred three more times?
Answers: 1
You know the right answer?
All of the following statements correctly describe a contemporary approach to create the work breakd...
Questions
question
Social Studies, 29.08.2019 22:30
Questions on the website: 13722367