subject

Which of these statements regarding time-cost tradeoffs in cpm networks is true?
a. crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
b. crashing is not possible unless there are multiple critical paths.
c. crashing a project often reduces the length of long-duration, but noncritical, activities.
d. the crash time always exceeds the normal time.
e. activities not on the critical path can never be on the critical path, even after crashing.

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 23:30
Me2540 week 5 assignment what do i want to know?
Answers: 1
question
Computers and Technology, 22.06.2019 21:30
This graph compares the total cost of attending educational institutions in texas. the graph demonstrates that the cost at private and public technical schools greatly varies.
Answers: 2
question
Computers and Technology, 23.06.2019 03:30
Hashtags serve to identify the topic of a given tweet true false
Answers: 2
question
Computers and Technology, 23.06.2019 09:30
After you present a proposal, the committee starts asking you questions, some beyond the strict focus of your proposal. they ask questions about implications in other fields and knowledge about other fields. you are asked to redo your proposal. what is most likely missing? breadth of material depth of material clarity of material details of material
Answers: 1
You know the right answer?
Which of these statements regarding time-cost tradeoffs in cpm networks is true?
a. crashing...
Questions
question
Mathematics, 15.01.2021 21:10
question
Mathematics, 15.01.2021 21:10
question
Arts, 15.01.2021 21:10
question
Mathematics, 15.01.2021 21:10
Questions on the website: 13722360