Ann is invited to help an Agile Release Train (ART) that has struggled through multiple Innovation and Planning (IP) Iterations. They just finished the second Iteration in the Program Increment (PI) and have nothing to demonstrate at the System Demo. Program stakeholders are really concerned.

What should Ann do?

a. Have every team demonstrate their team increment to the stakeholder separately in the team branch

b. Re-architect the system so that there are no dependencies between the teams, and integration is not needed

c. Stop working on any new functionality and fully integrate and trust the system, adjust scope based on learning

d. Re-plan the current PI. De-Scope to leave enough time to integrate what has been built during the IP iteration

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 24.06.2019 08:30
Aconsumer would pay an extra they used the rent to own program to buy the computer, rather than using cash. for all of the items, is the cheapest option over the life of the contract. the most expensive overall option is to use purchase the item.
Answers: 2
question
Computers and Technology, 24.06.2019 16:00
Which of the following characters is acceptable to use in a filename? ? / – %
Answers: 1
question
Computers and Technology, 24.06.2019 17:40
Create a file called favorite_foods, and list your favorite foods, entering five or six or more. press enter after each favorite food so it appears on its own line (make certain you also press enter after the final food item). after the file is created, add two more foods you like that are not on the list (press enter after the final food item). view the list of foods to make certain the two items you added appear at the end of the list
Answers: 2
question
Computers and Technology, 24.06.2019 19:20
Kiesha has a worksheet with a range of cells using the following columns: name, score, group, study group, and date. kiesha needs to sort the worksheet on the date field. which option she use to most efficiently complete this task ? a use the cut and paste option to reorganize the data to fit that order b use the filter function to organize the data based on the date c use the order function to organize the data based on the date d use the sort function to organize the data based on date order
Answers: 3
You know the right answer?
Ann is invited to help an Agile Release Train (ART) that has struggled through multiple Innovation a...
Questions
question
Health, 04.02.2021 14:00
question
Mathematics, 04.02.2021 14:00
question
Mathematics, 04.02.2021 14:00
question
Mathematics, 04.02.2021 14:00
question
Mathematics, 04.02.2021 14:00
Questions on the website: 13722363