For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time? a. the largest EF among the immediate predecessors b. the average EF among the immediate predecessors c. the largest LF among the immediate predecessors d. the difference in EF among the immediate predecessors

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 14:00
How are stop motion special effects in animated films created
Answers: 1
question
Computers and Technology, 24.06.2019 05:30
How do i get rid of my member ship for
Answers: 2
question
Computers and Technology, 24.06.2019 13:00
Which one of the following functions is not available on the autosum tool? sum average if max
Answers: 3
question
Computers and Technology, 24.06.2019 16:30
Pressing the backspace key deletes the text to the of the insertion point. the left or the right?
Answers: 1
You know the right answer?
For an activity with more than one immediate predecessor activity, which of the following is used to...
Questions
question
Mathematics, 06.05.2020 02:27
question
History, 06.05.2020 02:27
Questions on the website: 13722362