You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 01:30
How do you set up a slide show to play continuously, advancing through all the slides without requiring your interaction? a. click set up slide show, and then select the loop continuously until ‘esc' and show without narration options. b. click set up slide show, and then select the loop continuously until ‘esc' and use timings, if present options. c. click set up slide show, and then select the show presenter view and use timings, if present options. d. click set up slide show, and then select the show without animation and browsed at a kiosk (full screen) options.
Answers: 3
question
Computers and Technology, 23.06.2019 04:00
In a word processing program, such as microsoft word, which feature to you choose the desired picture enhancement?
Answers: 2
question
Computers and Technology, 25.06.2019 00:30
How do i take a screenshot on a laptop?
Answers: 2
question
Computers and Technology, 25.06.2019 08:30
What is the chief concern of cloud computing?
Answers: 1
You know the right answer?
You have just used the network planning model for a county road resurfacing project and found the cr...
Questions
Questions on the website: 13722361