A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 17:00
The two main ways in which marketers address the competition with their strategies are by satisfying a need better than a competition and by
Answers: 2
question
Computers and Technology, 22.06.2019 17:00
Aisha has finished working on a word processing document that contains 15 pages. she has added some special elements in the first three pages, page 9 and 10, and page 15 from the document. she wants to print only these pages to see how they look. which option is the correct way to represent (in the print dialog box) the pages that aisha wants to print
Answers: 3
question
Computers and Technology, 22.06.2019 20:00
When you mouse over and click to add a search term this(these) boolean operator(s) is(are) not implied. (select all that apply)?
Answers: 1
question
Computers and Technology, 22.06.2019 21:00
Describir textbook icon_person mira los dibujos y describe lo que está pasando. usa los verbos de la lista.
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
Questions on the website: 13722367