A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 22:50
Before you enter an intersection on a green light make sure
Answers: 2
question
Computers and Technology, 22.06.2019 00:30
Advantages and disadvantages of binary system
Answers: 1
question
Computers and Technology, 22.06.2019 04:30
Kyle, a receptionist for a building supply company, recently won an award for saving his company money on their phone system. after being presented with kyle's research, the company changed the way in which it made long-distance phone calls and cut their expenses in this area by 75 percent. the new system the kyle's company most likely adopted was wired communications switching stations voip hdtv
Answers: 3
question
Computers and Technology, 22.06.2019 20:00
Awide variety of “ apps “ are available to customize devices. which category of app does the word processing software fall into?
Answers: 2
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Social Studies, 31.05.2021 21:20
question
Mathematics, 31.05.2021 21:20
question
Mathematics, 31.05.2021 21:20
question
Physics, 31.05.2021 21:20
Questions on the website: 13722363