A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?
1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 08:00
Aplan to budget time for studying and activities is referred to as a study routine. study habits. study skills. a study schedule.
Answers: 1
question
Computers and Technology, 22.06.2019 22:10
Asequential circuit contains a register of four flip-flops. initially a binary number n (0000 ≤ n ≤ 1100) is stored in the flip-flops. after a single clock pulse is applied to the circuit, the register should contain n + 0011. in other words, the function of the sequential circuit is to add 3 to the contents of a 4-bit register. design and implement this circuit using j-k flip-flops.
Answers: 1
question
Computers and Technology, 22.06.2019 22:50
Which is the best minecraft server? a. mineplex b. worldonecraft c. 9b9t d. 2b2t
Answers: 2
question
Computers and Technology, 24.06.2019 10:00
In which view can you see speaker notes?
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 05.02.2022 08:40
question
Mathematics, 05.02.2022 08:40
question
English, 05.02.2022 08:40
Questions on the website: 13722363