A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 22:20
Pp 4.1 design and implement a class called sphere that contains instance data that represents the sphere’s diameter. define the sphere constructor to accept and initialize the diameter and include getter and setter methods for the diameter. include methods that calculate and return the volume and surface area of the sphere (see pp 3.5 for the formulas). include a tostring method that returns a one-line description of the sphere. create a driver class called multisphere, whose main method instantiates and updates several sphere objects.
Answers: 1
question
Computers and Technology, 23.06.2019 13:00
Which of the following statements is false? a. a class can directly inherit from class object. b. if the class you're inheriting from declares instance variables as private, the inherited class can access those instance variables directly. c. a class's instance variables are normally declared private to enforce good software engineering. d. it's often much more efficient to create a class by inheriting from a similar class than to create the class by writing every line of code the new class requires.
Answers: 3
question
Computers and Technology, 23.06.2019 22:20
What is a programming method that provides for interactive modules to a website?
Answers: 1
question
Computers and Technology, 24.06.2019 07:00
Selective is defined as paying attention to messages that are consistent with one’s attitudes and beliefs and ignoring messages that are inconsistent.
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 23.03.2021 06:40
question
Mathematics, 23.03.2021 06:40
question
Spanish, 23.03.2021 06:40
question
Mathematics, 23.03.2021 06:40
question
Mathematics, 23.03.2021 06:40
question
Mathematics, 23.03.2021 06:40
question
Mathematics, 23.03.2021 06:40
Questions on the website: 13722367