A project has a listing of tasks and durations (in days). A(5) starts and is followed by B(7). C(6) follows B. D(2) and E(5) continue after C, so does H(4). Once D, E and H are done, they move to J(2). G(8) starts and flows into H. 1. What are the paths and their durations.
2. What is the critical path?
3. What is the free slack for task B?
4. What is the free slack for task D?
5. What is the free slack for task E?
6. What is the free slack for task H?
7. What is the total slack for task G?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 11:00
How does a policy manual an organization? a. it boost productivity. b. it create awareness in employees about the organization’s values. c. it employees achieve targets. d. it safeguards the organization from liabilities.
Answers: 1
question
Computers and Technology, 22.06.2019 20:00
What statement best describes operating systems? it’s possible for modern computers to function without operating systems. most operating systems are free or very inexpensive. operating systems are managed by the computer’s microprocessor (cpu). operating systems manage the computer’s random access memory (ram).
Answers: 1
question
Computers and Technology, 23.06.2019 05:30
Sally is editing her science report about living things. she needs to copy a paragraph from her original report. order the steps sally needs to do to copy the text to her new document.
Answers: 1
question
Computers and Technology, 23.06.2019 10:20
Suppose there is a relation r(a, b, c) with a b+-tree index with search keys (a, b).1. what is the worst-case cost of finding records satisfying 10 < a < 50 using this index, in terms of the number of records n1, retrieved and the height h of the tree? 2. what is the worst-case cost of finding records satisfying 10 < a < 50 and 5 < b < 10 using this index, in terms of the number of records n2 that satisfy this selection, as well as n1 and h defined above? 3. under what conditions on n1 and n2, would the index be an efficient way of finding records satisfying the condition from part (2)?
Answers: 1
You know the right answer?
A project has a listing of tasks and durations (in days). A(5) starts and is followed by B(7). C(6)...
Questions
question
Mathematics, 23.09.2019 02:30
question
Mathematics, 23.09.2019 02:30
question
History, 23.09.2019 02:30
question
Social Studies, 23.09.2019 02:30
Questions on the website: 13722367