2. In a status report, executives want to know not only where we are today, but also where we will end up. Calculating where we will end up financially is not as easy as it sounds. Selecting the wrong formula can leave the executives and customers with a faulty impression. There are several formulas available for calculation of the estimated cost at completion (EAC). For simplicity, consider the following three formulas:
i. EAC = (AC(Total)/EV(Total)) x (budget at completion)
ii. EAC = ((AC(Total)/EV(Total)) x (PV for work completed and in progress)) + (planned or revised planned costs of work packages not yet begun)
iii. EAC = (actual to date) + (all remaining work, including work in progress, to be completed at the planned or budgeted costs)

a. Using the table below, determine the value of EAC for each of the three formulas. Assume that A, B, and C are the only work packages in the project, and PV(Total) is the total value for PV for each work package rather than PV for the reporting period. Similar to PV(Total), calculate AC(Total). Use the following formula for calculating EV(Total): EV(Total) = Sum of all EV(X), where X = A, B,C. EV(X)=% Complete * PV(X). Activity % Complete PV AC A 100 1000 1100 B 50 1000 800 C 0 1000 0
b. Considering only activity B, if the reason for the cost overrun is attributed to a one-time occurrence, which of the three formulas would be best to use?
c. If the reason for the overrun in activity B is because of the higher than expected salaries of the assigned employees and these same employees will be assigned to activity C as well, which of the three formulas would be best to use?
d. Considering only activity B, if the reason for the overrun is attributed to overtime and the overtime will continue but only through the completion of activity B, which of the three formulas would be best to use?
e. Considering your answers to the above four parts, should a company be willing to change the formula for calculating EAC during the execution of the project as well as at each reporting period or gate review meeting?

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 14:00
Which database model is best used for data warehouse and data mining
Answers: 3
question
Computers and Technology, 23.06.2019 02:00
Which of the following is not a source of sustainable raw materials? a) coal mine b) flick of sheep c) cotton plantation d) line forest.
Answers: 2
question
Computers and Technology, 23.06.2019 22:20
What is a programming method that provides for interactive modules to a website?
Answers: 1
question
Computers and Technology, 24.06.2019 07:00
You are most likely to automatically encode information about
Answers: 1
You know the right answer?
2. In a status report, executives want to know not only where we are today, but also where we will e...
Questions
question
Mathematics, 09.12.2020 22:00
question
English, 09.12.2020 22:00
question
Business, 09.12.2020 22:00
Questions on the website: 13722362